GASSMAKS-Økt verdiskaping fra naturgass

Basic energy efficient distillation technology

Separation of the components of natural gas into a set of product streams is a basic task for all kinds of natural gas processing. The problem is to obtain the valuable components sufficiently pure for further usage and conversion, and to carry out this s eparation with a minimum cost and energy ...

Awarded: NOK 10.1 mill.

Project Period: 2008-2012

Location: Trøndelag - Trööndelage

GASSMAKS-Økt verdiskaping fra naturgass

Revidert - Basic energy efficient distillation technology

This revised project shall be used to focus this proposal towards processes relevant for gas conversion. A survey in the area will be carried out and the research objective and research tasks will be defined more precisely. Original summary (refer to t he attached original project description)...

Awarded: NOK 0.30 mill.

Project Period: 2007-2007

Location: Trøndelag - Trööndelage

INTSAMGEN-Internasjonalt samarbeid generelt

Forprosjekt - Bilateralt samarbeid - Overordnet styring av store prosessanlegg

Bakgrunn SINTEF IKT har fra 2005 til 2008 fått innvilget et strategisk instituttprogram (SIP): "Optimal Design and Operation of Gas Processing Plants". (Prosjektnr 165818/I30 i NFR). Dette prosjektet er først og fremst rettet mot integrasjon mellom økon omi/marked og konsekvenser for overordnet...

Awarded: NOK 0.10 mill.

Project Period: 2005-2005

Location: Trøndelag - Trööndelage

SIPNKOMP-SIP-NHD: Andre nasjonalt viktige kompetansefelt

Optimal Design and Operation of Gas Processing Plants

The main issue in this project is to develop methodology for better market focus on process control and therby improved operation. Optimal operation of processing plants is a challenging area where new dynamic markets for gas components lead to a need fo r stronger analytical capabilities of dec...

Awarded: NOK 11.7 mill.

Project Period: 2005-2008