DEMO2000-Prosj.ret tekn.utv. petro.virk

Produksjonsoptimalisering og integritetsovervåkning av gassløft-brønner.

Alternative title: Optimized production, maintenance and well integrity surveillance on gas lifted oil wells

Awarded: NOK 7.5 mill.

The purpose of the project is to test a heli-portable unit with sensors for measuring pressure, flow and propagation of the tracer gas in wells. By placing sensors on the x-mas tree or wellhead and connect this to the software which describes propagation of the tracer gas from the process state (pressure, temperature and rate) and annular geometry (axial diameter and valve position) we will be able to monitor the production and/or identify leakage both in real time and over time. This information will give operators a new tool that will increase production by gas lift, prevent "healthy" wells killed, reducing the risk of leakage and monitoring wells that are ready for P&A.

Vi har oppnådd ønsket funksjonalitet som innebærer at løsningen kan måle strømninger og kalibrere løftegassrate for alle aktuelle brønner på et felt, uten at produksjonen må stoppes. Man kan ved bruk av vår teknologi kontinuerlig måle en rekke parametre og beregne løftegassrate og løftedybde(r) på hver enkelt brønn. Øyeblikksbilde og historiske data gjør at kunden kan foreta bedre justeringer. Løsningen har resultert i optimalisert produksjon med tilgjengelig mengde løftegass, samt at den forhindrer overforbruk av løftegass, nedetid av brønn, fører til enklere monitorering av status og definering av vedlikeholdsintervaller på delkomponentene i brønn. I tillegg til at PWOS kan brukes til optimaliserende tiltak, kan teknologien brukes til å identifisere lekkasjerate og lekkasjested (uønsket løftested). Teknologien har allerede blitt akseptert og tatt i bruk i markedet. Per i dag er det allerede utført jobber med PWOS-teknologi for flere millioner kroner.

Funding scheme:

DEMO2000-Prosj.ret tekn.utv. petro.virk